[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982986":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982986,712,2,"多选题","工程建设项目勘察、设计质量控制的方法有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","科学策划项目勘察、设计实施方案",true,{"key":16,"text":17,"correct":14},"B","合理选择勘察、设计供方单位",{"key":19,"text":20,"correct":14},"C","控制勘察、设计过程和设计深度",{"key":22,"text":23,"correct":14},"D","验收勘察成果、组织设计方案评审和施工图图纸会审",{"key":25,"text":26,"correct":27},"E","确保勘察、设计方案满足建设单位提出的各项功能要求",false,"ABCD","工程建设项目勘察、设计质量控制既是建设单位项目质量管理的重要内容，也是保证施工质量的重要条件，应系统实施相应的控制方法。具体包括：①科学策划项目勘察、设计实施方案；②组织勘察、设计招标活动；③合理选择勘察、设计供方单位；④协调勘察、设计过程；⑤控制勘察、设计过程和设计深度；⑥验收勘察成果、组织设计方案评审和施工图图纸会审；⑦控制设计变更质量。E项属于工程建设项目勘察、设计质量控制的内容。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]