[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982983":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982983,712,2,"多选题","设备正式调试的一般步骤包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","检查空负荷试车的确认文件和试车中出现的问题是否已经纠正",true,{"key":16,"text":17,"correct":18},"B","审查各项准备工作是否已满足试车的需要",false,{"key":20,"text":21,"correct":14},"C","做好试运行和带负荷试车方案与准备工作的落实",{"key":23,"text":24,"correct":14},"D","单项工程的带负荷试车",{"key":26,"text":27,"correct":14},"E","带负荷联动试车","ACDE","设备正式调试，又称带负载试车，其需要采取的步骤如下：①检查空负荷试车的确认文件和试车中出现的问题是否已经纠正；②做好试运行和带负荷试车方案与准备工作的落实；③单项工程的带负荷试车；④带负荷联动试车。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]