[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982974":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982974,712,2,"多选题","在项目的工程设计与计划阶段，业主与其聘请的管理咨询单位进度管理工作的重点是()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","对外管理好工程设计的进度",true,{"key":16,"text":17,"correct":18},"B","制订项目进度的总体规划",false,{"key":20,"text":21,"correct":18},"C","控制计划的推行",{"key":23,"text":24,"correct":18},"D","编制完整的项目进度管理体系",{"key":26,"text":27,"correct":14},"E","对内控制好编制项目各项预控计划（包括组织、进度、投资等）的进度","AE","B项是项目决策阶段业主与其聘请的管理咨询单位的工作重点；CD两项是在项目施工阶段业主与其聘请的管理咨询单位的工作重点。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]