[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982973":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982973,712,2,"多选题","工程技术与经济的分解决定了施工投标报价的方式，分解过程涉及()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","技术类型划分",true,{"key":16,"text":17,"correct":14},"B","市场价格",{"key":19,"text":20,"correct":14},"C","拟采用的承包管理实施方式",{"key":22,"text":23,"correct":24},"D","设计方案的优劣",false,{"key":26,"text":27,"correct":24},"E","施工方案的可操作性","ABC","工程技术与经济的分解决定了施工投标报价的方式。作为项目的业主或总承包单位，若进行所管理范围内项目的施工或供货的采购，必须先依照工作分解结构(WBS)的方法，分别对自己负责范围内的工程进行技术与经济的分解，形成合同网络图（合约规划）及分项采购成本的规划；分解过程涉及项目相关工程的技术类型划分、市场价格、拟采用的承包管理实施方式等，以便确定设计与施工任务衔接的方式、总承包单位与分包单位的合同及管理关系，并进而确定组织相应施工投标报价的方式。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]