[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982957":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982957,712,2,"多选题","项目需求分析的基本过程包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","直观描述项目的需求",true,{"key":16,"text":17,"correct":14},"B","评估和审核需求分析报告",{"key":19,"text":20,"correct":14},"C","利用示意图形象表达客户需求",{"key":22,"text":23,"correct":14},"D","建立项目需求跟踪系统",{"key":25,"text":26,"correct":27},"E","分析需求的反馈意见",false,"ABCD","项目需求分析的基本过程包括：①确定和排列客户需求重点。把客户需求转化为项目需求，进而设计项目的技术路线。②直观描述项目的需求。③利用示意图形象表达客户需求。④建立项目需求跟踪系统。准确预测环境及市场的变化，预测客户需求的可能变化，建立项目需求跟踪系统是需求分析及管理中的一项重要工作。⑤评估和审核需求分析报告。需求报告的初稿完成后，应组织项目发起人、客户以及其他相关的项目利益相关方对报告进行评估和审核，在共同讨论后达成一致的意见。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]