[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982934":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982934,712,2,"多选题","下列关于项目管理目标的制订与落实的说法中，正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","制订项目管理目标需具备一定的技术基础和管理条件",true,{"key":16,"text":17,"correct":18},"B","工作任务书是表述项目目标的唯一载体",false,{"key":20,"text":21,"correct":14},"C","项目管理目标体系应与项目绩效考核相结合",{"key":23,"text":24,"correct":18},"D","项目管理目标的制定者应是实现目标的执行者",{"key":26,"text":27,"correct":14},"E","工作分解结构是确定目标参数的主要依据之一","ACE","B项，项目范围管理中的“项目许可证”、“工作任务书”、“工作分解结构”这三项重要管理成果既是确定目标参数的主要依据，又是表述目标管理的最适宜的载体，还是由浅入深对项目整体及分解目标做出的制约性描述；D项，项目管理目标的制订只能由项目发起人承担，其他的参与方只能在自己的合同与责任范围内制订子项目或者相应部分的分解管理目标。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]