[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982929":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982929,712,2,"多选题","项目动态管理的过程包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","检查",true,{"key":16,"text":17,"correct":14},"B","实施",{"key":19,"text":20,"correct":21},"C","反馈",false,{"key":23,"text":24,"correct":14},"D","计划",{"key":26,"text":27,"correct":14},"E","处理与改进","ABDE","通用的过程动态管理方法称为PDCA循环方法：①计划(Plan)。针对项目或过程目标制订相关目标、程序、方法和详细计划。②实施(Do)。从资源投入到成果实现，协调各方及资源以执行计划。③检查(Check)。不断监测和分析工作进展，预防目标偏离。④处理与改进(Act)。对可能出现的偏差进行分析，采取持续改进管理工作，通过变更调整计划的处理措施。PDCA循环方法体现了过程管理的严格控制和持续改进的要求。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]