[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982923":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982923,712,2,"多选题","下列关于招标采购信息管理的描述，正确的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","招标采购信息管理不是孤立的信息处理，而是必然影响和涉及项目信息管理的其他部分。",true,{"key":16,"text":17,"correct":14},"B","招标采购信息记录主要包括招标采购文件与招标采购过程记录两方面",{"key":19,"text":20,"correct":21},"C","招标采购信息收集的内容只有与招标采购活动相关的法律、法规资料",false,{"key":23,"text":24,"correct":14},"D","招标采购信息的收集应采取的措施包括标准化措施和制度措施",{"key":26,"text":27,"correct":21},"E","招标文件反映招标采购活动的实质性内容，经过当事人一方的认可后，具有法律效力","ABD","C项，招标采购信息收集的内容还包括工程项目和产品信息、供应商信息、采购案例信息；E项，招标文件反映招标采购活动的实质性内容，经过当事人双方的认可后，具有法律效力。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]