[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982917":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982917,712,2,"多选题","招标采购工作检查应包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","招标采购工作现状",true,{"key":16,"text":17,"correct":14},"B","招标采购项目未来趋势",{"key":19,"text":20,"correct":21},"C","招标采购项目的盈利空间",false,{"key":23,"text":24,"correct":21},"D","招标采购项目资源安排情况",{"key":26,"text":27,"correct":14},"E","招标采购工作中里程碑事件状况","ABE","招标采购工作检查应包括：①招标采购工作的现状；②招标采购项目的未来趋势；③招标采购工作中里程碑事件的状况；④招标采购任务完成后的检查。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]