[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982915":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982915,712,2,"多选题","招标采购活动质量控制的目标有()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","采购合同完善无歧义",true,{"key":16,"text":17,"correct":14},"B","采购签约价格合理低价",{"key":19,"text":20,"correct":14},"C","采购程序合法规范",{"key":22,"text":23,"correct":24},"D","采购在计划周期内完成",false,{"key":26,"text":27,"correct":24},"E","采购过程费用合理","ABC","质量、成本、进度是项目管理的三大主要管理目标，招标采购的实施控制结果与项目本身的质量、进度、成本控制紧密相连。对项目的质量、进度和成本的控制结果不仅体现了采购团队工作质量和水平，而且是保证项目招标采购成功、降低项目风险的重要标志。招标采购项目质量控制的目标如表所示。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]