[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982907":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982907,712,2,"多选题","一个项目的投标文件的组成内容应包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","投标函部分",true,{"key":16,"text":17,"correct":14},"B","技术部分",{"key":19,"text":20,"correct":14},"C","商务部分",{"key":22,"text":23,"correct":24},"D","报价部分",false,{"key":26,"text":27,"correct":24},"E","经济部分","ABC","在对招标采购项目计划进行实施和检查时，要检查投标人的投标文件是否齐全。投标文件的组成内容应当包括：投标函部分、商务部分、技术部分。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]