[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982893":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982893,712,2,"多选题","在工程招标中，进度规划的内容有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","工程建设程序",true,{"key":16,"text":17,"correct":14},"B","招标相关工作顺序和时间安排",{"key":19,"text":20,"correct":21},"C","工程建设项目衔接配套",false,{"key":23,"text":24,"correct":14},"D","工程项目的细分",{"key":26,"text":27,"correct":21},"E","采购货物名称","ABD","依不同的采购标的，总进度规划的内容分别为：①工程招标，主要有工程项目的细分、工程建设程序、工程总进度规划、招标相关工作顺序和时间安排以及相关责任主体等；②货物招标，主要有采购货物名称、数量、技术指标、时间节点、顺序安排和工程建设项目或生产需求的衔接配套和相关责任主体等；③服务招标，主要有服务内容、目标要求、需求特点、时间安排和相关责任主体等；④对于复杂项目，如进口机电产品招标的管理等，还应补充国际采购的特殊环节予以说明。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]