[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982878":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982878,712,2,"多选题","在项目跟踪中，属于项目的内部因素跟踪的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资金使用情况",true,{"key":16,"text":17,"correct":18},"B","政策制度",false,{"key":20,"text":21,"correct":14},"C","项目人员投入",{"key":23,"text":24,"correct":18},"D","自然环境",{"key":26,"text":27,"correct":14},"E","组织责任落实情况","ACE","项目的内部因素主要包括合同履行当事人的人员投入、资金使用情况、资源到位程度、设备运行情况、组织责任落实情况等。BD两项属于项目的外部因素的跟踪。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]