[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982870":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982870,712,2,"多选题","招标采购项目控制的措施中，下列各项属于采购费用控制措施的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","减少额外费用支出",true,{"key":16,"text":17,"correct":18},"B","掌握项目总体进度对招标采购项目计划时间的要求",false,{"key":20,"text":21,"correct":14},"C","建立费用管理（申报、报销等）制度、标准及审核、审批程序",{"key":23,"text":24,"correct":14},"D","合理安排人力资源，避免间歇式工作，采用招标项目群管理方式，充分利用信息和共享资源",{"key":26,"text":27,"correct":18},"E","准确、完整的理解委托人的意图，提供完整的备案资料，与行政监督管理部门充分沟通，及时反馈过程问题","ACD","招标采购费用控制的措施主要包括：①采购团队应合理安排人力资源、避免间歇式工作、采用招标项目群管理方式；②充分利用信息和共享资源；③建立费用管理（申报、报销等）制度、标准及审核、审批程序以及厉行节约；④减少额外费用支出等。BE两项属于招标采购项目进度控制的措施。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]