[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982865":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982865,712,2,"多选题","招标采购进度计划制订的依据包括()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","项目采购时间要求",true,{"key":16,"text":17,"correct":14},"B","项目采购的特点",{"key":19,"text":20,"correct":14},"C","项目采购的技术经济条件",{"key":22,"text":23,"correct":14},"D","招标采购各项工作的时间估计",{"key":25,"text":26,"correct":27},"E","招标采购各项工作的人员组合",false,"ABCD","制订进度计划的依据主要包括：①项目采购时间要求；②项目采购的特点；③项目采购的技术经济条件；④招标采购各项工作的时间估计；⑤限制和约束。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]