[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982863":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982863,712,2,"多选题","招标采购工作中，招标采购工作费用估计的主要依据包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","WBS",true,{"key":16,"text":17,"correct":14},"B","历史信息",{"key":19,"text":20,"correct":14},"C","资源价格",{"key":22,"text":23,"correct":24},"D","采购人员的工资",false,{"key":26,"text":27,"correct":14},"E","工作的延续时间","ABCE","招标采购工作费用估计的主要依据包括：①工作分解结构(WBS)；②资源需求计划；③资源价格；④工作的延续时间；⑤历史信息，包括项目文件、可共用的项目费用估计数据库及项目工作组的相关经验等。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]