[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982857":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982857,712,2,"多选题","在责任分配矩阵中，()是项目经理通常担当的角色与责任。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","执行工作",true,{"key":16,"text":17,"correct":14},"B","部分或参与决策",{"key":19,"text":20,"correct":21},"C","控制成本",false,{"key":23,"text":24,"correct":14},"D","必须通报的",{"key":26,"text":27,"correct":21},"E","控制质量","ABD","在责任分配矩阵中，项目管理通常有五种角色和责任，分别为：①X表示执行工作；②D表示单独或决定性决策；③d表示部分或参与决策；④C表示必须咨询的；⑤I表示必须通报的。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]