[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982853":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982853,712,2,"多选题","招标采购计划实施过程中，检查计划实施情况的重点内容有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标采购工作的人员组成",true,{"key":16,"text":17,"correct":18},"B","招标采购费用支出",false,{"key":20,"text":21,"correct":18},"C","招标采购委托合同",{"key":23,"text":24,"correct":14},"D","招标采购中面临的风险",{"key":26,"text":27,"correct":14},"E","招标采购工作进度","ADE","招标采购项目实施的检查内容比较复杂，具体内容方面的检查包括：①招标采购方案内容及其相关影响因素；②招标文件的使用情况；③招标采购工作进度的符合性；④招标采购工作的人员组成与招标需求的衔接程度；⑤招标采购过程的相关方信息反馈；⑥招标采购项目面临的风险和不确定性的判别和控制。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]