[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982848":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982848,712,2,"多选题","关于招标采购项目管理，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","招标采购质量控制的目标是确保招标程序合法，价格合理低价",true,{"key":16,"text":17,"correct":18},"B","招标采购成本和费用控制的目标是使采购成本和费用最低",false,{"key":20,"text":21,"correct":18},"C","可以利用工作结构分解方法来进行招标采购质量控制",{"key":23,"text":24,"correct":14},"D","招标采购进度控制的目标是满足建设项目整体进度的要求",{"key":26,"text":27,"correct":14},"E","可以通过采取事前预测，事中检查、纠正，事后总结、评价来达到招标采购质量控制的目标","ADE","B项，招标采购成本和费用控制的目标是在满足质量、进度要求的前提下使采购成本和费用最低。C项，利用工作结构分解方法可以进行招标采购进度控制，不能进行招标采购质量控制。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]