[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982842":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982842,712,2,"多选题","工作先后依赖关系包括()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","隶属关系",false,{"key":16,"text":17,"correct":14},"B","协调关系",{"key":19,"text":20,"correct":21},"C","组织关系",true,{"key":23,"text":24,"correct":14},"D","工序关系",{"key":26,"text":27,"correct":21},"E","工艺关系","CE","工作先后依赖关系是指招标采购各工作的执行安排需遵守工作之间先后制约关系的限制，进而决定工作的安排次序，任何工作的执行必须依赖于一定工作的完成，即它的执行必须在某些工作完成之后才能执行。工作先后依赖关系有两种：①工作之间本身存在的、无法改变的工艺关系，如设计与生产关系；②人为确定的、两项工作可先可后的组织关系。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]