[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982835":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982835,712,2,"多选题","已知某工程的双代号网络计划如图所示，下列说法正确的有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","该计划的工期为12天",true,{"key":16,"text":17,"correct":18},"B","工作④一⑥最早开始时间为4天",false,{"key":20,"text":21,"correct":18},"C","关键线路为①一③一⑤一⑥",{"key":23,"text":24,"correct":14},"D","工作②一⑥为非关键工作",{"key":26,"text":27,"correct":14},"E","关键线路为①一②一④一⑥","ADE","A项，关键线路的长度即为该计划的工期，即2+6+4=12（天）；B项，工作④一⑥最早开始时间为②一④工作和①一③工作最早完成时间的最大值，即8天；CE两项，该双代号网络计划中，关键线路为①—②一④一⑥。D项，工作2-6不在关键线路上，因此为非关键工作。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]