[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982832":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982832,712,2,"多选题","项目沟通管理的主要工作过程有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","组建项目组织",false,{"key":16,"text":17,"correct":18},"B","编制沟通计划",true,{"key":20,"text":21,"correct":18},"C","信息发布",{"key":23,"text":24,"correct":18},"D","编制绩效报告",{"key":26,"text":27,"correct":14},"E","薪酬管理","BCD","项目沟通管理主要包括以下工作过程：①识别利益相关方，识别所有受项目影响的人员或组织，并记录其利益、参与情况和对项目成功的影响；②规划沟通，确定项目利益相关方的信息需求，并定义沟通方法；③发布信息，按计划向项目利益相关方提供相关信息；④管理利益相关方期望，为满足利益相关方的需要而与之沟通和协作，并解决所发生的问题；⑤报告绩效，收集并发布绩效信息（包括状态报告、进展测量结果和预测情况）。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]