[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982829":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982829,712,2,"多选题","项目中各项工作之间的逻辑关系具体表现为()等关系。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","平行",true,{"key":16,"text":17,"correct":18},"B","交叉",false,{"key":20,"text":21,"correct":18},"C","螺旋",{"key":23,"text":24,"correct":14},"D","顺序",{"key":26,"text":27,"correct":14},"E","搭接","ADE","排列活动顺序是指确定各工作之间的逻辑关系，并形成成果文档。工作之间的逻辑关系（先后顺序关系）主要包括工艺关系和组织关系，具体可表现为平行、顺序和搭接三种形式。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]