[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982828":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982828,712,2,"多选题","在项目时间管理中，估算活动持续时间的准确性主要依赖于()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","对项目的质量要求",false,{"key":16,"text":17,"correct":14},"B","项目范围定义",{"key":19,"text":20,"correct":21},"C","对项目工作了解程度",true,{"key":23,"text":24,"correct":21},"D","可以参考的历史经验",{"key":26,"text":27,"correct":14},"E","工作人员的个人经验","CD","估算活动持续时间需要依据活动工作范围、所需资源类型、所需资源数量以及资源日历等，进行活动持续时间估算。这类估算的准确性主要依赖于对项目工作了解程度和可以参考的历史经验，所以一般由对项目工作最熟悉、经验最丰富的个人和集体承担。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]