[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982825":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982825,712,2,"多选题","S曲线的绘制步骤包括()。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","编制项目进度计划的横道图",true,{"key":16,"text":17,"correct":14},"B","根据每单位时间内完成的工作或者投入的人力、物力和财力，计算单位时间（月、旬或周）的成本，在时标网络图上按时间编制成本计划",{"key":19,"text":20,"correct":14},"C","计算规定时间内计划累计支出的成本额",{"key":22,"text":23,"correct":24},"D","依据成本额衡量各项活动的重要性",false,{"key":26,"text":27,"correct":14},"E","根据累计计划成本，绘制S曲线","ABCE","S曲线是指根据计划成本在相应的工程活动上的成本分配，在时间坐标上绘制出时间一成本累计曲线，因为形状如字母S而得名。S曲线的绘制步骤包括：①编制项目进度计划的横道图；②根据每单位时间内完成的工作或者投入的人力、物力和财力，计算单位时间（月、旬或周）的成本，在时标网络图上按时间编制成本计划；③计算规定时间内计划累计支出的成本额；④根据累计计划成本，绘制S曲线。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]