[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982823":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982823,712,2,"多选题","单代号网络计划图（见图）中，关键线路有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","A→B→E→G→I",false,{"key":16,"text":17,"correct":18},"B","A→B→E→H→I",true,{"key":20,"text":21,"correct":14},"C","A→C→E→G→I",{"key":23,"text":24,"correct":18},"D","A→C→E→H→I",{"key":26,"text":27,"correct":14},"E","A→C→F→H→I","BD","关键线路是指总工作持续时间最长的线路。图中的线路有：①A→B→D→G→I，工期为18天；②A→B→E→G→I，工期为18天；③A→B→E→H→I，工期为19天；④A→C→E→G→I，工期为18天；⑤A→C→E→H→I，工期为19天；⑥A→C→F→H→I，工期为18天。即关键线路为③和⑤。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]