[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982820":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982820,712,2,"多选题","项目成本管理一般包括三个阶段性的任务，即包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","估算成本",true,{"key":16,"text":17,"correct":18},"B","制定成本计划",false,{"key":20,"text":21,"correct":14},"C","制订预算",{"key":23,"text":24,"correct":14},"D","控制成本",{"key":26,"text":27,"correct":18},"E","进行成本核算","ACD","项目成本管理一般包括三个阶段性任务：①估算成本，是对完成项目活动所需资金进行近似估算的过程；②制订预算，是汇总所有单个活动或工作包的估算成本，建立一个经批准的成本基准的过程；③控制成本，是监督项目状态以更新项目预算、管理成本基准变更的过程。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]