[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982818":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982818,712,2,"多选题","在项目生命周期的开始阶段，最适宜的成本计划管理方法有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","预算",false,{"key":16,"text":17,"correct":18},"B","估算",true,{"key":20,"text":21,"correct":18},"C","匡算",{"key":23,"text":24,"correct":14},"D","概算",{"key":26,"text":27,"correct":14},"E","精算","BC","在项目生命周期的开始阶段，项目的技术文件尚不确定，对成本只需作出匡算和估算，虽然不够精确，但不失为最适宜的成本计划管理方法。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]