[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982813":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982813,712,2,"多选题","挣值分析的评价指标包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","费用偏差",true,{"key":16,"text":17,"correct":18},"B","价值指数",false,{"key":20,"text":21,"correct":14},"C","进度偏差",{"key":23,"text":24,"correct":14},"D","进度绩效指数",{"key":26,"text":27,"correct":14},"E","费用绩效指数","ACDE","挣值分析的评价指标包括：①费用偏差，是指检查日期EV与AC之间的差异；②进度偏差，是指检查日期EV与PV之间的差异；③费用绩效指数，是指EV与AC之比；④进度绩效指数，是指EV与PV之比。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]