[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982810":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982810,712,2,"多选题","针对项目范围变更的控制行为包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","争取变更向对自己有利的方向发展",true,{"key":16,"text":17,"correct":18},"B","确保正确、满意地完成项目范围变更提及的全部工作",false,{"key":20,"text":21,"correct":18},"C","对项目在执行过程中完成的各项工作进行及时检查",{"key":23,"text":24,"correct":14},"D","按照程序核实确认已经和将要发生的范围变更",{"key":26,"text":27,"correct":14},"E","结合进度、费用、质量控制和合同管理等其他管理任务，妥善处理已经发生的范围变更","ADE","项目范围变更是指对已经明确项目范围定义的改变，可能涉及增减项目工作、改变项目成果数量和功能要求等。针对项目范围变更的控制行为包括：①争取变更向对自己有利的方向发展；②按照程序核实确认已经和将要发生的范围变更，杜绝“范围蔓延”；③结合进度、费用、质量控制和合同管理等其他管理任务，妥善处理已经发生的范围变更。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]