[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982806":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982806,712,2,"多选题","下列方法中，属于网络计划技术的有()。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","计划评审技术",true,{"key":16,"text":17,"correct":14},"B","关键路径法",{"key":19,"text":20,"correct":21},"C","横道图",false,{"key":23,"text":24,"correct":21},"D","管理软件",{"key":26,"text":27,"correct":21},"E","因素分析法","AB","网络计划是指用网络图表达工作构成、工作顺序并加注工作时间参数的进度计划。有两种基本的网络计划：①计划评审技术(PERT)，是一种基于概率分析的网络计划技术，其关注的重点是工作的开始事件和完成事件。PERT经常用于不确定性较强项目的进度控制可能性分析。②关键路径法(CPM)。通过对关键路径的控制，大大地缩短了项目的进度。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]