[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982805":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982805,712,2,"多选题","监控项目工作过程涉及()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","把项目的预期绩效与项目管理计划进行比较",false,{"key":16,"text":17,"correct":18},"B","评估项目绩效，决定是否需要采取纠正或预防措施，并推荐必要的措施",true,{"key":20,"text":21,"correct":18},"C","识别新风险，分析、跟踪和监测已有风险，确保全面识别风险、报告风险状态，并执行适当的风险应对计划",{"key":23,"text":24,"correct":18},"D","做出预测，来更新当前的成本与进度信息",{"key":26,"text":27,"correct":18},"E","在已批准的变更实际发生时，监督其实施情况","BCDE","监控项目工作过程涉及：①把项目的实际绩效与项目管理计划进行比较；②评估项目绩效，决定是否需要采取纠正或预防措施，并推荐必要的措施；③识别新风险，分析、跟踪和监测已有风险，确保全面识别风险、报告风险状态，并执行适当的风险应对计划；④在整个项目期间，维护一个准确并及时更新的信息库，来反映项目产品及相关文件的情况；⑤为状态报告、进展测量和预测提供信息；⑥做出预测，来更新当前的成本与进度信息；⑦在已批准的变更实际发生时，监督其实施情况。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]