[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982803":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},982803,712,2,"多选题","因果分析图的作图步骤包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","进行可行性分析",false,{"key":16,"text":17,"correct":18},"B","选定质量特性",true,{"key":20,"text":21,"correct":18},"C","确定影响质量特性的原因",{"key":23,"text":24,"correct":18},"D","查漏补遗",{"key":26,"text":27,"correct":18},"E","确定关键原因","BCDE","因果分析图的作图步骤包括：①选定质量特性；②确定影响质量特性的原因；③对影响质量的一级原因作进一步分析，找出其中存在的具体原因，并分别标注各自大枝的分枝上；④查漏补遗；⑤确定关键原因；⑥制订对策。",{"id":6,"name":31,"category":32,"favorite":33},"招标采购项目管理","建筑工程",0]