[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982800":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982800,712,1,"单选题","投融资服务项目范围变更应遵循()的过程。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","申请—审查—确认—实施",true,{"key":16,"text":17,"correct":18},"B","申请—确认—实施",false,{"key":20,"text":21,"correct":18},"C","申请—确认—变更",{"key":23,"text":24,"correct":18},"D","申请—变更—确认—实施","在投融资服务项目实施期间，业主有权在合同范围内对服务项目进行变更。变更应遵循“申请—审查—确认—实施”的过程，如果变更导致咨询服务的工作量和工作内容增加，还应该考虑增加咨询服务费。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]