[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982747":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982747,712,1,"单选题","关于接收建议书，下列说法不正确的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","先提交技术建议书，再提交财务建议书",true,{"key":16,"text":17,"correct":18},"B","不得接收在截止时间后提交的对技术建议书或财务建议书的修改",false,{"key":20,"text":21,"correct":18},"C","如有必要，客户应延长提交建议书的截止时间",{"key":23,"text":24,"correct":18},"D","任何在提交建议书截止时间后收到的建议书都应原封退回","A项，委托人应给予服务方一定的时间来准备其建议书。给予的时间视服务项目情况而定，但一般不应少于4周或超过3个月。技术建议书和财务建议书应同时提交，不得接收在截止时间后提交的对技术建议书或财务建议书的修改。为了保证程序的诚信，技术建议书和财务建议书应分别装在密封的信封中提交。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]