[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982737":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982737,712,1,"单选题","()适用于服务内容和期限以及要求服务方提交的成果能够明确规定的服务项目。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","百分比合同",false,{"key":16,"text":17,"correct":18},"B","总价合同",true,{"key":20,"text":21,"correct":14},"C","顾问服务合同",{"key":23,"text":24,"correct":14},"D","成本加酬金合同","总价合同主要适用于服务内容和期限以及要求服务方提交的成果能够明确规定的服务项目。这类合同被广泛应用于简单的规划和可行性研究、标准或普通建筑物的详细设计、程序化的数据处理系统等。A项，百分比合同直接将付给服务方的费用与项目建设估算成本联系起来，或与所采购或检验的货物的成本联系起来；C项，顾问服务合同适用于委托人对某些服务活动具有不定期的需求，服务的程度和时间在事前是无法确定，同时又希望服务方能够“随叫随到”，这时通常采用不定期服务合同；D项，成本加酬金合同是在经双方讨论同意的估算成本的基础上，再加上一笔报酬金额的计费方法。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]