[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982692":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982692,712,1,"单选题","工程咨询服务项目的管理过程包括：①明确客户需求；②综合分析，提出建议（咨询报告）；③收集数据信息、进行分析；④提供阶段性结果；⑤确定项目，组建项目小组；⑥初步接洽；⑦制订工作计划；⑧工作总结；⑨协助实施。正确的顺序是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","⑥—①—⑤—⑦—③—④—⑨—②—⑧",false,{"key":16,"text":17,"correct":18},"B","⑥—①—⑤—⑦—③—④—②—⑨—⑧",true,{"key":20,"text":21,"correct":14},"C","①—⑥—⑤—⑦—③—④—⑨—②—⑧",{"key":23,"text":24,"correct":14},"D","①—⑥—⑤—⑦—③—④—②—⑨—⑧","工程咨询服务项目的管理过程是：①初步接洽；②明确客户需求；③确定项目，组建项目小组；④制订工作计划；⑤收集数据信息、进行分析；⑥提供阶段性结果；⑦综合分析，提出建议（咨询报告）；⑧协助实施；⑨工作总结。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]