[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982649":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982649,712,1,"单选题","下列关于项目可行性研究工作内容的描述，错误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","项目可行性研究报告的封闭上报",false,{"key":16,"text":17,"correct":14},"B","制订项目的筹融资方案及资金使用计划",{"key":19,"text":20,"correct":21},"C","分析、论证项目设计总进度目标",true,{"key":23,"text":24,"correct":14},"D","参加项目可行性研究报告评估和审核，协助办理相关报批手续","项目可行性研究工作的内容包括：①结合中标设计方案情况进行投入产出分析，编制项目总投资估算，进行项目总投资切块；②编制项目实施总进度规划，包括设计、招标采购、施工等全过程；③制订项目的筹融资方案及资金使用计划；④确定项目的质量要求和建造标准；⑤项目可行性研究报告的封闭上报；⑥参加项目可行性研究报告的评估和审核，协助办理相关报批手续。C项属于设计进度计划管理与监控的工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]