[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982644,712,1,"单选题","下列关于采购计划编制工作的说法，错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","采购计划编制的工作主要包括采购计划的编制和审核",true,{"key":16,"text":17,"correct":18},"B","合同条款的前瞻性与预防施工风险的有效性应有机衔接，保证采购成果满足施工风险预防需求，施工合同和监理合同符合施工管理有效性的需求",false,{"key":20,"text":21,"correct":18},"C","在工程建设设备采购招标时，应该明确对设备的设计、生产、到货验收等过程实施监督、管理、控制和协调，售后的零部件采购和保修服务也应在采购前予以考虑",{"key":23,"text":24,"correct":18},"D","依据工程项目的进度需求实施采购计划，业主组织编制各招标文件和合同文件中有关进度的条款，设置逾期处罚及补救办法，需要时起草甲控材料设备的清单、控制内容及程序要求","A项，采购计划编制的工作主要包括：①采购计划的制订；②采购计划的执行。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]