[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982635":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982635,712,1,"单选题","关于工程建设项目的质量目标，下列叙述有误的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","质量目标是项目建设的基本目的",false,{"key":16,"text":17,"correct":14},"B","目标的制定应该力求把质量风险降到最低",{"key":19,"text":20,"correct":21},"C","工程项目的质量管理应围绕着致力于满足政府的质量目标而展开",true,{"key":23,"text":24,"correct":14},"D","工程建设项目的质量目标，是业主建设意图通过项目策划和目标决策提出的","C项，业主工程项目的质量管理，包括勘察设计、招标投标、施工安装、竣工验收等各阶段，均应围绕致力于满足业主的质量目标而展开。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]