[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982634":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982634,712,1,"单选题","下列关于社会评价的说法错误的是()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","调查的基本社会经济情况包括人际关系、户籍资料和文化水平",true,{"key":16,"text":17,"correct":18},"B","经常采用的调查分析方法有文献查阅法、问卷调查法、访谈、座谈会等",false,{"key":20,"text":21,"correct":18},"C","社会评价所需调查的资料范围是受项目影响区域在项目影响时限内的社会经济情况",{"key":23,"text":24,"correct":18},"D","受项目影响的利益群体是调查社会资料的维度之一","A项，社会评价所需调查的资料范围是受项目影响区域在项目影响时限内的社会经济情况。可以从两个维度进行调查：①基本社会经济情况，包括人口统计资料、基础设施与服务设施状况，当地的风俗习惯、人际关系；②受项目影响的利益群体，分析各利益群体对项目的反应、要求与接受程度及各利益群体参与项目活动的可能性等。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]