[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982632":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982632,712,1,"单选题","在管理承包模式(M C)中，业主要求管理承包商提出保证最大工程费用。关于实际工程费用的说法，正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","超支部分由管理承包商承担，结余部分归业主所有",false,{"key":16,"text":17,"correct":14},"B","超支部分由业主承担，结余部分归管理承包商所有",{"key":19,"text":20,"correct":21},"C","超支部分由管理承包商承担，结余部分由管理承包商与业主分成",true,{"key":23,"text":24,"correct":14},"D","超支部分由业主承担，结余部分由管理承包商与业主分成","一般来讲，业主均要求管理承包商(MC)提出保证最大工程费用，作为MC的承包基数，投资一旦超支则由MC承担，如有结余则与业主分成。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]