[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982623":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},982623,712,1,"单选题","设计单位介入项目是在()。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目的策划决策阶段",true,{"key":16,"text":17,"correct":18},"B","项目设计阶段",false,{"key":20,"text":21,"correct":18},"C","项目计划阶段",{"key":23,"text":24,"correct":18},"D","项目施工阶段","设计单位最初是在项目的策划决策阶段以设计或技术的咨询方式介入项目的，可能是项目功能策划、工艺设计及技术顾问，或是参加概念设计的征集与建筑方案设计的投标。在这个阶段，设计单位工作较为单一，与其他参与方的协调较少，一般只是按业主或其聘请的管理咨询单位指定的时间限期完成咨询任务即可，进度管理较为单纯。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]