[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982621":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982621,712,1,"单选题","按照计价方式不同，建设工程合同可分为总价合同、单价合同和成本加酬金合同，其中成本加酬金合同主要适用于()的工程建设项目。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","风险水平较高",false,{"key":16,"text":17,"correct":14},"B","风险水平较低",{"key":19,"text":20,"correct":14},"C","技术简单",{"key":22,"text":23,"correct":24},"D","技术复杂",true,"实行工程量清单计价的工程应采用单价合同，对于建设规模较小，技术难度较低，工期较短，且施工图设计已审查批准的建设工程可采用总价合同，而对于施工技术特别复杂的建设工程可采用成本加酬金合同。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]