[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982613":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982613,712,1,"单选题","下列关于项目进度管理体系中三级计划间关系的说法错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","一、二、三级计划间是对应的",false,{"key":16,"text":17,"correct":14},"B","二级计划与一级计划是对应的",{"key":19,"text":20,"correct":14},"C","三级计划与二级计划是对应的",{"key":22,"text":23,"correct":24},"D","三级计划与一级计划间不存在联系",true,"项目管理体系中一、二、三级计划间的对应，二级计划与一级计划是对应，而三级计划与二级计划及一级计划也是对应的。进度管理体系中的各类计划尽管编制方不同，目的与作用不同，但因都是基于一个共同的进度平台而编制，所以主要的时间节点完全相互对应。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]