[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982612":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982612,712,1,"单选题","在风险转移的途径中，利用()来降低或规避某些风险的转移成本相对较低。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程保险",false,{"key":16,"text":17,"correct":14},"B","工程担保",{"key":19,"text":20,"correct":21},"C","合同的保护性条款",true,{"key":23,"text":24,"correct":14},"D","工程贷款","工程建设项目风险管理广泛使用的风险转移方式有：①设定保护性合同条款；②工程担保；③工程保险。在三种转移途径中，利用合同的保护性条款来降低或规避某些风险的转移成本相对较低。工程担保和保险需要向被转移者支付一定的风险保障费用，而设置保护性条款的转移费用支出是隐性的，不必直接支付转移费用。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]