[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},982611,712,1,"单选题","下列关于经济效果的评价方法的说法错误的是()。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","动态评价方法是考虑资金时间价值以进行项目评价的方法",false,{"key":16,"text":17,"correct":14},"B","静态评价方法最大特点是计算简便",{"key":19,"text":20,"correct":14},"C","静态评价方法不考虑资金时间价值",{"key":22,"text":23,"correct":24},"D","在进行方案比较时，一般以静态评价方法为主",true,"D项，经济效果的评价方法，按其是否考虑时间因素分为静态评价方法和动态评价方法。在进行方案比较时，一般以动态评价方法为主。在方案初选阶段，可采用静态评价方法。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]