[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982610":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982610,712,1,"单选题","工程设计质量管理工作的具体内容不包括()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","安排施工图的强制性审查",false,{"key":16,"text":17,"correct":14},"B","组织安排编制工程量清单及施工图预算，确保预算准确且不超过给定的投资控制指标及浮动的限度",{"key":19,"text":20,"correct":21},"C","作出技术设计的具体工作安排",true,{"key":23,"text":24,"correct":14},"D","组织全部施工图的质量审查，最大限度地减少各专业施工图纸的“错、漏、碰、缺”","工程设计质量管理工作的具体内容包括：①采用价值工程方法，在充分满足项目功能要求的条件下进一步考虑设计的可建性、材料的可获得性，采用新技术新工艺来优化各级设计，以挖掘节约投资的潜力；②安排施工图的强制性审查；③组织全部施工图的质量审查，最大限度地减少各专业施工图纸的“错、漏、碰、缺”；④组织初步设计与施工图设计的符合性审查；⑤组织初步设计概算的审查；组织安排编制工程量清单及施工图预算。C项属于技术设计工作安排的工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]