[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982606":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},982606,712,1,"单选题","下列关于设计一招标一施工模式(DB B)的说法，不正确的是()。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","业主只进行一次施工招标并与一个施工单位签订施工总承包合同",false,{"key":16,"text":17,"correct":14},"B","该模式管理的技术基础是线性顺序法，所以具有该方法固有的缺陷，即耗时较长",{"key":19,"text":20,"correct":21},"C","国外在工地现场多采用委托施工监理的方式，国内则采取管理公司派出驻地工程师的方式",true,{"key":23,"text":24,"correct":14},"D","该模式工作界面清晰，特别适用于项目各个阶段需要严格逐步审批的情况","C项，设计一招标一施工模式(DBB)的特点之一是：项目施工阶段的管理协调已作为一种专业独立出来，以确保项目管理达到较高水平。国外在工地现场多采取管理公司派出驻地工程师方式，国内则为委托施工监理方式。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]