[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-982596":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},982596,712,1,"单选题","下列各项中，()不属于项目初步决策阶段业主的管理工作内容。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","项目建设必要性的环境调查",false,{"key":16,"text":17,"correct":18},"B","项目可行性研究工作",true,{"key":20,"text":21,"correct":14},"C","技术策划",{"key":23,"text":24,"correct":14},"D","宏观经济分析","项目初步决策阶段业主的管理工作内容包括：①项目建设必要性的环境调查；②宏观经济分析；③技术策划；④编制并报批项目建议书。B项属于项目设计准备与审定决策阶段业主的管理工作内容。",{"id":6,"name":27,"category":28,"favorite":29},"招标采购项目管理","建筑工程",0]